top of page
Writer's pictureGabriel Mikael

How long Does Each Process and Stages would Take in Home Building

The duration of each stage in the home-building process can vary depending on the size and complexity of the project, the weather conditions, and the availability of materials and labor. Here's a general timeline for each phase of building a home in Cagayan de Oro:

1. Planning and Budgeting

Duration: 1-3 months

The planning stage involves setting a budget, finalizing the design with your architect, and choosing a contractor. It’s essential to invest time in this stage to ensure all aspects of the project are considered, including materials, design preferences, and construction costs.

  • Architectural Design: This step can take 2-4 weeks depending on how quickly you finalize the house plans with your architect.

  • Contractor Selection: Choosing a reputable contractor and agreeing on terms typically takes 1-2 weeks.

2. Securing Land and Permits

Duration: 1-2 months

  • Land Purchase: This can take from a few days to several weeks, depending on how quickly the purchase process is completed, including title transfer.

  • Permit Acquisition: Getting the necessary building permits from the Office of Building Official (OBO) in Cagayan de Oro can take anywhere from 2-6 weeks. The timeline depends on the completeness of your application and how busy the local government offices are.

3. Site Preparation and Foundation

Duration: 1-2 months

  • Site Clearing and Excavation: This typically takes 1-2 weeks, depending on the size of the lot and the amount of clearing required.

  • Foundation Construction: Laying the foundation can take 2-4 weeks, depending on the type of foundation required (e.g., raised foundation in flood-prone areas). Concrete curing time is also a factor, which can add another week or two.

4. Structural Work: Framing, Roofing, and Walls

Duration: 2-3 months

  • Framing: Building the framework of the house typically takes 3-6 weeks. This includes erecting the structural supports and beams.

  • Roofing: Installing the roof usually takes 1-2 weeks, depending on the materials used and the complexity of the roof design.

  • Wall Construction: Building exterior and interior walls takes about 2-4 weeks. Prefabricated panels or advanced systems can speed up the process.

5. Utilities Installation: Electrical, Plumbing, and HVAC

Duration: 1-2 months

This stage includes the installation of electrical wiring, plumbing, and HVAC systems. Utility installation is done after framing and before finishing the walls.

  • Plumbing and Electrical Work: This can take 3-6 weeks depending on the size of the house and the complexity of the systems.

  • Inspection: Expect 1-2 weeks for inspection by local authorities, though it could be quicker if everything is up to code.

6. Interior and Exterior Finishing

Duration: 2-4 months

This stage involves everything from drywall installation to painting, flooring, and installing cabinets and fixtures.

  • Interior Finishing: Tasks like drywall, tiling, and painting can take 6-12 weeks depending on the complexity of the interior work.

  • Exterior Finishing: Installing windows, doors, and exterior paint or siding usually takes 3-6 weeks.

7. Final Inspection and Handover

Duration: 1-2 weeks

Once the house is fully constructed, a final inspection will be conducted by local authorities to ensure everything complies with building regulations. After the inspection is passed, you can obtain your Certificate of Occupancy, allowing you to move in.

Overall Construction Timeline

Total Time: 8-12 months

On average, the entire process of building a house in Cagayan de Oro, from planning to moving in, can take 8 to 12 months. This timeline can extend for larger, more complex homes or shorten if you’re building a simpler design.

Factors That Can Affect the Timeline

  • Weather Conditions: Cagayan de Oro’s rainy season can slow down outdoor work like roofing and foundation laying.

  • Material Delays: Shortages of construction materials or delays in delivery can affect the schedule.

  • Contractor and Labor Availability: A busy contractor may have multiple projects running simultaneously, potentially causing delays.


How long Does Each Process and Stages would Take in Home Building
How long Does Each Process and Stages would Take in Home Building

Recent Posts

See All

Kommentare


bottom of page