top of page

Why permits delay projects and how we prevent it

Permits usually get delayed because submissions are incomplete, non-compliant, or changed after filing—so the application gets returned for corrections. In CDO, the Building Official requires specific sets of forms, proof of ownership, multiple plan sets, and professional licenses; incomplete applications are not accepted.

The real reasons permits delay projects


1) Incomplete document set

CDO’s Building Permit checklist explicitly requires (among others):

  • 4 copies of the Unified Application Form

  • proof of ownership (OCT/TCT/Deed of Sale/lot locational plan)

  • 4 sets of plans/documents (architectural, structural, electrical, sanitary/plumbing, etc.)

  • photocopies of valid PRC licenses of involved professionals

  • notarized estimated building value

  • Construction Safety & Health Program + Affidavit of Undertaking…and it clearly states: only complete and compliant applications will be accepted.


2) Missing fire-related requirements

Even at occupancy stage, CDO’s checklist requires proof tied to fire safety documentation (e.g., FSEC copy) as part of the Certificate of Occupancy packet.


3) Plan changes after submission

Changing layout, adding floor area, moving walls/openings, or revising MEP after filing often triggers rework in documents and re-routing approvals (a common delay driver).


4) Backlog + routing across offices

LGU processing capacity and multi-step routing can slow things down, especially when applicants don’t follow up or don’t respond quickly to “return for compliance.” Research on permit service quality points to staff capacity and incomplete compliance as recurring issues.


5) Occupancy gets delayed because turnover docs are not ready

CDO’s Certificate of Occupancy checklist requires: Unified application form, notarized Certificate of Completion (Annex H) signed by owner and licensed professional (and contractor signatory if contracted), construction logbook, approved plans/ancillary permits, PRC licenses, photos of completed structure, and more. National Building Code guidance also ties occupancy release to final inspection and submission of completion documents.


How we prevent permit delays (our control system)


1) Pre-permit “Document Audit” (before we print anything)

We use a checklist-based audit against CDO’s requirements (forms, ownership, plan sets, PRC IDs, notarized declarations, safety docs) so the application doesn’t bounce.

2) “Permit-ready plans” rule (no half-baked drawings)

We don’t submit until the plan set is complete across disciplines required for your project (architectural + structural + electrical + sanitary/plumbing, etc.).

3) Freeze the scope before submission

We lock:

  • target floor area

  • room count + layout

  • wall system/openings

  • wet areas + MEP routing. So we don’t trigger plan revisions mid-permit. (This alone prevents the most painful delays.)

4) Assign one accountable “Permit Owner”

One person owns: submission date, claim stub tracking, follow-up schedule, and compliance turnaround. CDO’s checklist even emphasizes keeping the claim stub for release and follow-ups.

5) Parallel prep for Occupancy from Day 1

We set up the Occupancy folder early (logbook discipline, photo documentation, completion forms planning), so occupancy doesn’t stall at turnover.


Want our copy-paste CDO Permit + Occupancy Checklist Pack (with a homeowner-friendly “what to prepare” version)? Comment PERMIT.


Why permits delay projects and how we prevent it
Why permits delay projects and how we prevent it

Comments


Contact Us

Wallpro Systems & Const Inc

2F RPM Bldg. Golden Glow North Commercial Macapagal Rd., Upper Carmen Cagayan de Oro

9000, Philippines

+63917-5156755

OPENING HOURS

Mon - Fri: 8:00 AM - 5:00 PM

Sat: 8:00 AM - 12:00 PM

© 2023 by Wallpro Systems & Construction Inc. All rights reserved.

Thanks for submitting!

bottom of page