top of page

How Long Will the Whole Project Take From Design to Turnover?

Most residential builds (lot owners) typically take 4 to 9 months from design start to turnover, depending on permit readiness, house size, storeys, and finish level.

  • Fast-track (simple design + complete documents + flat lot): ~4–6 months

  • Typical (custom design + normal approvals + standard finishes): ~6–9 months

  • Complex (2-storey, many upgrades, siteworks/retaining, frequent changes): ~9–12+ months


The Real Timeline Breakdown (End-to-End)

Phase 1: Planning + Design (3–8 weeks)

What happens:

  • Requirements interview + budget alignment

  • Concept layout (space planning)

  • Design development (final room sizes, windows, roof, elevations)

  • Engineering coordination + signed/sealed plans

  • Initial BOQ/specs alignment (so design matches budget)


Typical duration: 3–8 weeks Big delay trigger: changing the room count/layout after costing.

Phase 2: Permits + Clearances (2–6+ weeks)

If documents are complete, government service standards target shorter processing windows (often framed under “simple/complex/highly technical” timelines). In practice, real timelines expand when there are revisions, missing signatures, or queued inspections.


Typical duration: 2–6+ weeksBig delay trigger: incomplete requirements, re-submission cycles.

Phase 3: Pre-Construction (1–3 weeks)

What happens:

  • Final BOQ + specs freeze (what is included/excluded)

  • Procurement plan (long-lead items: windows/doors, roofing, tiles, cabinets)

  • Mobilization (temporary facilities, site layout, safety)


Typical duration: 1–3 weeks

Phase 4: Construction Proper (3–10 months depending on size/complexity)

Quick guide by house type

  • 40–60 sqm bungalow: 10–14 weeks

  • 60–90 sqm bungalow: 12–18 weeks

  • 90–130 sqm bungalow: 16–24 weeks

  • 80–120 sqm 2-storey: 20–32 weeks

  • 120–180 sqm 2-storey: 28–40 weeks

What affects this the most:

  • Roof complexity

  • Number of bathrooms (waterproofing + tiling time)

  • Custom cabinetry scope

  • Weather + curing windows

  • Siteworks surprises (soft soil, drainage, retaining)


Phase 5: Punchlist + Testing + Turnover (2–4 weeks)

What happens:

  • Final inspection/punchlist

  • Corrections, cleaning, commissioning (basic testing)

  • Turnover documentation (warranty, as-built notes if provided)


Typical duration: 2–4 weeks

Phase 6: Occupancy / Certificate of Occupancy (often overlaps; 1–3+ weeks)

Don’t skip this: under PD 1096 rules, a building generally shouldn’t be used/occupied without the required occupancy clearance/certificate.


The 7 Things That Delay Projects Most Often

  1. Changing layout midstream (bedroom moves, bigger kitchen, extra T&B)

  2. Permits with incomplete documents (resubmissions)

  3. Late finish decisions (tiles, fixtures, lights, paint system)

  4. Siteworks surprises (drainage, hauling, retaining)

  5. Material lead times (windows/doors/cabinets/custom items)

  6. Weather + curing time (especially during prolonged rains)

  7. Cashflow timing (delayed releases slow procurement and manpower)


How to Hit a Target Move-In Date (Simple System)

How Long Will the Whole Project Take From Design to Turnover?
How Long Will the Whole Project Take From Design to Turnover?

Comments


Contact Us

Wallpro Systems & Const Inc

2F RPM Bldg. Golden Glow North Commercial Macapagal Rd., Upper Carmen Cagayan de Oro

9000, Philippines

+63917-5156755

OPENING HOURS

Mon - Fri: 8:00 AM - 5:00 PM

Sat: 8:00 AM - 12:00 PM

© 2023 by Wallpro Systems & Construction Inc. All rights reserved.

Thanks for submitting!

bottom of page