How Long Will the Whole Project Take From Design to Turnover?
- Gabriel Mikael
- 7 minutes ago
- 2 min read
Most residential builds (lot owners) typically take 4 to 9 months from design start to turnover, depending on permit readiness, house size, storeys, and finish level.
Fast-track (simple design + complete documents + flat lot): ~4–6 months
Typical (custom design + normal approvals + standard finishes): ~6–9 months
Complex (2-storey, many upgrades, siteworks/retaining, frequent changes): ~9–12+ months
The Real Timeline Breakdown (End-to-End)
Phase 1: Planning + Design (3–8 weeks)
What happens:
Requirements interview + budget alignment
Concept layout (space planning)
Design development (final room sizes, windows, roof, elevations)
Engineering coordination + signed/sealed plans
Initial BOQ/specs alignment (so design matches budget)
Typical duration: 3–8 weeks Big delay trigger: changing the room count/layout after costing.
Phase 2: Permits + Clearances (2–6+ weeks)
If documents are complete, government service standards target shorter processing windows (often framed under “simple/complex/highly technical” timelines). In practice, real timelines expand when there are revisions, missing signatures, or queued inspections.
Typical duration: 2–6+ weeksBig delay trigger: incomplete requirements, re-submission cycles.
Phase 3: Pre-Construction (1–3 weeks)
What happens:
Final BOQ + specs freeze (what is included/excluded)
Procurement plan (long-lead items: windows/doors, roofing, tiles, cabinets)
Mobilization (temporary facilities, site layout, safety)
Typical duration: 1–3 weeks
Phase 4: Construction Proper (3–10 months depending on size/complexity)
Quick guide by house type
40–60 sqm bungalow: 10–14 weeks
60–90 sqm bungalow: 12–18 weeks
90–130 sqm bungalow: 16–24 weeks
80–120 sqm 2-storey: 20–32 weeks
120–180 sqm 2-storey: 28–40 weeks
What affects this the most:
Roof complexity
Number of bathrooms (waterproofing + tiling time)
Custom cabinetry scope
Weather + curing windows
Siteworks surprises (soft soil, drainage, retaining)
Phase 5: Punchlist + Testing + Turnover (2–4 weeks)
What happens:
Final inspection/punchlist
Corrections, cleaning, commissioning (basic testing)
Turnover documentation (warranty, as-built notes if provided)
Typical duration: 2–4 weeks
Phase 6: Occupancy / Certificate of Occupancy (often overlaps; 1–3+ weeks)
Don’t skip this: under PD 1096 rules, a building generally shouldn’t be used/occupied without the required occupancy clearance/certificate.
The 7 Things That Delay Projects Most Often
Changing layout midstream (bedroom moves, bigger kitchen, extra T&B)
Permits with incomplete documents (resubmissions)
Late finish decisions (tiles, fixtures, lights, paint system)
Siteworks surprises (drainage, hauling, retaining)
Material lead times (windows/doors/cabinets/custom items)
Weather + curing time (especially during prolonged rains)
Cashflow timing (delayed releases slow procurement and manpower)
How to Hit a Target Move-In Date (Simple System)
Freeze floor area + layout early (sqm changes = timeline changes)
Set a finish decision deadline (tiles/fixtures/paint/lighting)
Require a weekly update (photos + progress vs schedule)
Lock long-lead items before structure finishes
Use a written change order (VO) rule: no work without signed approval
#CagayanDeOroConstructionCompany #CDOHomeBuilder #HouseConstructionPH #BuildTimeline #HomeBuildingGuide #DesignToTurnover #BuildingPermitPH #BOQ #ConstructionPhases #Punchlist #Turnover #LotOwnerPH #BudgetBuildPH #BuildSmart #ProjectManagement




Comments