top of page

How Long Will the Whole Project Take From Design to Turnover?

Most residential builds (lot owners) typically take 4 to 9 months from design start to turnover, depending on permit readiness, house size, storeys, and finish level.

  • Fast-track (simple design + complete documents + flat lot): ~4–6 months

  • Typical (custom design + normal approvals + standard finishes): ~6–9 months

  • Complex (2-storey, many upgrades, siteworks/retaining, frequent changes): ~9–12+ months


The Real Timeline Breakdown (End-to-End)

Phase 1: Planning + Design (3–8 weeks)

What happens:

  • Requirements interview + budget alignment

  • Concept layout (space planning)

  • Design development (final room sizes, windows, roof, elevations)

  • Engineering coordination + signed/sealed plans

  • Initial BOQ/specs alignment (so design matches budget)


Typical duration: 3–8 weeks Big delay trigger: changing the room count/layout after costing.

Phase 2: Permits + Clearances (2–6+ weeks)

If documents are complete, government service standards target shorter processing windows (often framed under “simple/complex/highly technical” timelines). In practice, real timelines expand when there are revisions, missing signatures, or queued inspections.


Typical duration: 2–6+ weeksBig delay trigger: incomplete requirements, re-submission cycles.

Phase 3: Pre-Construction (1–3 weeks)

What happens:

  • Final BOQ + specs freeze (what is included/excluded)

  • Procurement plan (long-lead items: windows/doors, roofing, tiles, cabinets)

  • Mobilization (temporary facilities, site layout, safety)


Typical duration: 1–3 weeks

Phase 4: Construction Proper (3–10 months depending on size/complexity)

Quick guide by house type

  • 40–60 sqm bungalow: 10–14 weeks

  • 60–90 sqm bungalow: 12–18 weeks

  • 90–130 sqm bungalow: 16–24 weeks

  • 80–120 sqm 2-storey: 20–32 weeks

  • 120–180 sqm 2-storey: 28–40 weeks

What affects this the most:

  • Roof complexity

  • Number of bathrooms (waterproofing + tiling time)

  • Custom cabinetry scope

  • Weather + curing windows

  • Siteworks surprises (soft soil, drainage, retaining)


Phase 5: Punchlist + Testing + Turnover (2–4 weeks)

What happens:

  • Final inspection/punchlist

  • Corrections, cleaning, commissioning (basic testing)

  • Turnover documentation (warranty, as-built notes if provided)


Typical duration: 2–4 weeks

Phase 6: Occupancy / Certificate of Occupancy (often overlaps; 1–3+ weeks)

Don’t skip this: under PD 1096 rules, a building generally shouldn’t be used/occupied without the required occupancy clearance/certificate.


The 7 Things That Delay Projects Most Often

  1. Changing layout midstream (bedroom moves, bigger kitchen, extra T&B)

  2. Permits with incomplete documents (resubmissions)

  3. Late finish decisions (tiles, fixtures, lights, paint system)

  4. Siteworks surprises (drainage, hauling, retaining)

  5. Material lead times (windows/doors/cabinets/custom items)

  6. Weather + curing time (especially during prolonged rains)

  7. Cashflow timing (delayed releases slow procurement and manpower)


How to Hit a Target Move-In Date (Simple System)

How Long Will the Whole Project Take From Design to Turnover?
How Long Will the Whole Project Take From Design to Turnover?

Recent Posts

See All

Comments


Wallpro System & Construction Inc | All Rights Reserved.
Cagayan de Oro
bottom of page